SUNRISE POWERLINK DRAFT ENVIRONMENTAL IMPACT REPORT
PUBLIC MEETING
February 26, 2008
Thank you Commissioner Gruenich and Judge Weissman for holding this and other
public hearings in communities most impacted by this line.
I represent the people of San Diego County’s Second District, which encompasses the
eastern portion of San Diego County. My district includes many communities affected
by San Diego Gas and Electric’s Sunrise Powerlink proposal including Ramona, Julian
and Santa Ysabel, as well as many communities along Alternative Route D in the
southeastern part of the region.
The County of San Diego is finalizing its formal comments on the Draft Environmental
Report (EIR) and will submit those technical comments before the April 11, 2008
deadline. I have reviewed the Draft EIR, in particular its executive summary.
I remain steadfastly opposed to the project in its entirety, including the Preferred Route
and Alternative Route D. As the Draft EIR points out, there are cheaper and less
destructive ways to meet future energy needs.
If speakers here tonight seem especially upset, it’s because this area is still reeling from
the massive firestorms of last October, fires likely started by SDG&E power lines.
In addition, the region has endured SDG&E’s controversial Sunrise campaign for more
than two years. This divisive effort has pitted rural communities against urban
communities and tried to turn northern communities against southern communities.
Fortunately, many of us have seen through SDG&E’s propaganda. SDG&E has
presented the CPUC’s decision as a choice: approve Sunrise or suffer rolling blackouts.
Yet, as the Draft EIR thankfully indicates— and as expert after expert has testified—
Sunrise is a false choice. The EIR’s top two alternatives clearly show that this
region— its economy and its landscape— are better served by local, not imported,
generation.
In commercials and glossy brochures, SDG&E’s impressive public relations machine
has boiled down the pitch for Sunrise into a snappy soundbite. SDG&E says this: “Sunrise will bring us the three Rs: renewables, reliability and reduced costs.”
Unfortunately, SDG&E overlooked a forth and more important R: reality.
Here’s the reality about renewables: There is enough capacity on the existing
Southwest Powerlink to bring wind, solar and geothermal energy from the Imperial
Valley into this region without building Sunrise.
SDG&E’s own testimony reveals that the utility can meet California’s renewable
mandate without building Sunrise.
The unproven Stirling Solar Dish project— the cornerstone of SDG&E’s renewable
claims— has been delayed again. The company has not filed an application for
construction with the California Energy Commission. Worse yet, Stirling officials have
testified they will move forward with a type of technology that has long suffered from
hydrogen and engine-seal leaks.
Finally, if SDG&E is as committed to renewable energy as it claims, why— last
summer— did the company lobby against increasing the State’s renewable mandate?
Here’s the reality about reliability: A massive extension chord through our fire-prone
Backcountry does not equal greater reliability. It equals perilous danger.
In my discussions with SDG&E, the utility used the 2003 Cedar Fire as an interesting
argument for Sunrise. SDG&E said that Sunrise was needed because if the existing
Southwest Powerlink were to go down in a fire, Sunrise could ensure reliability.
SDG&E officials downplayed the likelihood of the region having two massive fires at
the same time. That argument was debatable until October 2007. It turned out SDG&E
was right. We didn’t have two massive fires at the same time. We had seven!
The Southwest Powerlink went down in the Harris fire. And, had Sunrise been built, it
would have been out of service too because of the path of the Witch Fire.
Here’s the reality about reduced cost: Repeatedly, we have seen the alleged financial
benefits of Sunrise drop dramatically because of SDG&E’s own miscalculations, math
errors and faulty assumptions about power plants. First it was $447 million, then $204
million, then $129 million— less than one quarter of the line’s original cost savings
estimates.
The Utility Consumers Action Network and other energy stakeholder groups have done
some remarkable research into the cost-effectiveness of upgrading exiting
infrastructure and investing in solar— proposals that have largely been ignored by
SDG&E.
It’s time for SDG&E to retire claims about the three Rs. The facts don’t support them. The region needs to turn its focus to the three Es— existing infrastructure, emerging
technologies and efficiency measures.
The State of California is standing at the threshold of a whole new era in energy
development. In my mind, Sunrise is really a battle between the dying past and the
promising future.
California, with its Million Solar Roofs campaign and its investments in energy
research, is blazing trails when it comes to renewables. The State and its Governor
have put its money where its mouth is. That investment is paying off.
This month, a story in NY Times, describes California as the world’s “next big solar
market and its entrepreneurial center.” An economist said of California: “We’re at the
dawn of a revolution that could be as powerful as the Internet revolution.” A venture
capitalist said companies are just starting to blossom from venture funding and,“through innovation and volume, prices are coming down.”
Change is scary and SDG&E is likely protecting an old way of doing business.
Yet the financial sector and the energy sector are all saying the same thing: hulking
lines and massive steel are antiquated concepts. Distributed generation, self-reliance
and new green technologies are here to stay, whether SDG&E likes it or not. Imported
power— in Sunrise’s case, much of it from fossil-fueled plants— is a thing of the past.
By approving Sunrise, California would be building a billion dollar monument to the
past. It will be outdated before it’s even finished.
By turning down this line, the Commission sends an important message to the San
Diego region: San Diegans need to create in-basin generation and become selfsufficient
and safer from fire.
With your help, we can force our utility to do the right thing.
Thank you again for the opportunity to speak this evening.